Excerpts from 12/22/10
correspondence with Secretary Chu's CMRR-NF/UPF Review
Panel
...I thought you might be interested in this
little "value engineering" check on the current direction
of CMRR-NF. If we assume HazCat II space is "apples,"
and HazCat III/IV space is "oranges," I look at the value
NNSA is getting in terms of "apples" + "oranges,"
i.e. "fruit." As you can see NNSA downscoped this
project considerably as far as the useful space is concerned, even
as the cost has gone through the roof. I think the percentage
increase in estimated cost is much greater than any large project in
NNSA's history to date. The "balloon factor" is
larger than any of the large DOE projects examined in GAO's
2007 review (pdf).
Most of my assumptions are shown.
All the data is from congressional budget requests and one (2001) Ten
Year Site Plan. Slightly different results can be obtained
under different assumptions regarding the limited data set, but the
overall result doesn't change appreciably or in qualitative terms.
I
got the (approximate) 38,500 sq. ft. of useful space from NNSA
project managers last year and I assume it hasn't changed.
Initially, CMRR-NF was supposed to have 60% of its 200,000 gross sq.
ft. of interior building area devoted to programmatic purposes.
Now it is about 9.5% (of 406,000 gross sq. ft.). Overall
concrete requirements have increased since 2003 by a factor of
116.
I see a decline in estimated value (i.e. product
obtained/dollar spent) at CMRR-NF by about a factor of 45, or more if
one assumes the 2003 square footage of useful area was what LANL and
NNSA had in mind earlier, in 2001 and 2002.
Needless to
say there has also been an erosion in compliance with DOE Order
413.3, which was put in place after reviews by GAO and the National
Research Council to prevent this kind of outcome. We are still
2-3 years from a baseline on this project, as I understand it, even
though design is about half completed.
To me, the direction toward
which this all trends is that somebody, whether this committee or
some other, should examine alternatives. Unfortunately, NNSA
has not developed any yet.
Year |
CMRR-NF |
CMRR
Total |
HazCat
II |
HazCat
III/IV |
Total
Useful |
$
per Useful |
Ratio
of Value |
Notes |
|
TPC,
$M |
w/
D&D |
space,
sq. ft. |
space,
sq. ft. |
CMRR-NF |
sq.
ft. |
from
2003 |
|
2001 |
251 |
375 |
60,000? |
60,000? |
120,000? |
2,092? |
1.59? |
1 |
2002 |
361 |
525 |
60,000? |
60,000? |
120,000? |
3,008? |
1.11? |
2 |
2003 |
400 |
600 |
60,000 |
60,000 |
120,000 |
3,333 |
1.00 |
3 |
2004 |
400 |
600 |
22,000 |
23,000 |
45,000 |
8,889 |
0.37 |
4 |
2005 |
561 |
1,238 |
38,500 |
0 |
38,500 |
14,571 |
0.23 |
5 |
2006 |
561 |
1,238 |
38,500 |
0 |
38,500 |
14,571 |
0.23 |
6 |
2007 |
561 |
1,238 |
38,500 |
0 |
38,500 |
14,571 |
0.23 |
7 |
2008 |
2,000 |
2,564 |
38,500 |
0 |
38,500 |
51,948 |
0.06 |
8 |
2009 |
2,000 |
2,564 |
38,500 |
0 |
38,500 |
51,948 |
0.06 |
9 |
Feb-10 |
3,389 |
4,195 |
38,500 |
0 |
38,500 |
88,029 |
0.04 |
10 |
Nov-10 |
5,800 |
6,563 |
38,500 |
0 |
38,500 |
150,649 |
0.02 |
11 |
Notes: |
1.
Initial cost used to justify project to DOE in LANL Ten-Year Site
Plan |
2.
Initial midpoint cost presented to Congress in PED; assumes $100 M
OPC as in following year; assumes CMRR-NF is 2/3 of total CMRR. |
3.
Initial line item estimate; assumes CMRR-NF is 2/3 of total CMRR
for lack of better data |
4.
Assumes CMRR-NF is 2/3 of total CMRR estimate for lack of better
data |
5.
Assumes CMRR-NF is 2/3 of total CMRR estimate for lack of better
data |
6.
Assumes CMRR-NF is 2/3 of total CMRR estimate for lack of better
data |
7.
Assumes CMRR-NF is 2/3 of total CMRR estimate for lack of better
data |
8.
Minimum CMRR-NF cost shown as per request |
9.
Minimum CMRR-NF cost shown as per request |
10.
Includes stated contingency |
11.
High point of range but omits CMR maintenance & any upgrades,
CMR D&D, and applicable portion of NMSSUP |
Yesterday I spoke with a former member of
the NRC panel which worked to improve DOE project management from 1999 to 2003.
This team, the members of which worked on a voluntary basis,
criss-crossed the country and spoke to about 200 DOE people and a
number of outside experts over these years, and produced a number of
reports. Yesterday he felt that little or nothing had improved
at DOE as a result of their labors. As many people told the
team, the cost of DOE projects was set from the top down, i.e. set
politically, not managerially as in the private sector. Project
scope, as the team wrote in their
1999 report, was treated by DOE as a contingency, i.e. was set
(up or down) by DOE's perception of what the market would bear (NRC,
1999, electronic page 39). It's a sorry picture, and I could
tell it was depressing to him. It would be (and is) to me too.
The CMRR-NF project breaks most of DOE's most important project
management rules, and the cost and schedule fallout is evident.
It is incredible to me that it is being allowed to proceed under
these conditions, with DOE's project management rules in tatters
beneath.
A kind of monomaniacal blindness seems to have arisen
regarding CMRR-NF wherein no alternatives to the project are deemed
possible, even though project realities have changed so greatly.
No price, it appears lately, is too great to pay, although exactly
what capabilities would be bought is not fully apparent. The
scrutiny once provided by Congress and even by OMB for the first few
months of this Administration, is temporarily absent. GAO is
silent. The building has become a token of larger meanings, a symbol of nuclear preparedness rather than a rational tool, and God knows
what else. It is beginning to feel a bit like the pursuit of
the White Whale in Moby
Dick.
This morning I worked up the table below, using a variety
of sources and modeling the 2005 CMRR-NF cost at 2/3 of the stated
CMR cost overall. The inflator used is the CPI-U; costs are
Total Project Costs (TPCs).
Facility |
Year |
HazCat
II space, sq. ft. |
Cost
then, $millions (M) |
Inflator |
Cost
now, $M |
Constant
$
HazCat
II sq. ft. |
CMR
(wings 1, 2, 3, 4, 5, & 7) |
1954 |
44,000 |
21 |
8.13 |
172 |
3,909 |
PF-4 |
1978 |
59,600 |
75 |
4.07 |
305 |
5,117 |
CMRR-NF |
2005 |
38,500 |
629 |
1.12 |
704 |
18,298 |
CMRR-NF |
2010 |
38,500 |
5800 |
1.00 |
5800 |
150,649 |
Taking the long view, it is
possible that these high capitol costs, which are more than an order
of magnitude greater than during the Cold War in constant dollars,
and which will be augmented by equally-increased operating costs
relative to the CMR facility today (which has an extremely low
maintenance cost, especially since it is being inappropriately run to
failure or replacement, whichever comes first), will prove to be
incompatible with effective maintenance of a nuclear deterrent.
That is the view of some with whom I have spoken. Said
differently, the CMRR-NF behemoth may simply be too inelegant to be
practical. A surprising number of people believe it is too
ambitious to be successfully built. On balance I think NNSA
might manage to get it built, but I am not sanguine about its future
operation, or about the quality of science that would surround
it.
You have received my little Chinese menu of CMRR-NF
alternatives (The
Proposed Chemistry and Metallurgy Research Replacement Nuclear
Facility (CMRR-NF): New Realities Call for New Thinking, pdf, Dec
10, 2010). Another restaurant would have a different, but
overlapping menu. I have not checked out the competition yet,
nor do I know if there is any active. But I am sure the prices
in NNSA's restaurant are too high, so out of line it's a wonder they
can stay in business.
I omitted some items on that short menu,
such as moving the facility to a nearby location at LANL that did not
have the offending unconsolidated ash layer. I limited myself
to 4 pages.
What I do not know well, or know precisely, is
what the customer really needs, and how those needs are generated by
present and future contingent policies. The customer's wants
are more or less infinite, of course -- bird's nest soup today, then
endangered tiger, and on up to unicorn or whatever. The fact is
that at some point in this spectrum of wants -- we don't know for
sure what that point is -- the restaurant will go broke, and the
customer will starve or lose interest waiting for the gourmet meal. Clarifying
this matter of purpose and need would be helpful.
At present NNSA has kept it as clear as mud. By
failing to clarify project scope, NNSA assures CMRR-NF design is
a so-called "wicked problem," in which the evolving
solutions redefine the problem to be solved.
More sarcastically, to what extent is CMRR-NF (with the "hotel
concept") a $5.8 billion answer looking for a question -- a
hotel, looking for lodgers?
We
do not know the mission elements needed for the plutonium mission.
No one with money and clearances has studied how these missions line
up with the capacities, present and contingent, of existing and
planned facilities, or in general what the most elegant and
cost-effective solutions might be. Six billion dollars -- and
now CMRR is likely to cost more than that, with RLUOB, CMR D&D,
not to mention the security fence -- would buy a lot of remodeling
and planning.
I
therefore recommend that your panel consider the wisdom of having
somebody seriously study this problem prior to NNSA investing further in what may be an overpriced capability of dubious true utility, or
worse, a fiasco....
|