new banner
about us home contact contribute blog twitter search

SFNM

LANL's prototype plutonium bomb core passes key tests

By Scott Wyland swyland@sfnewmexican.com
Feb 19, 2024

Los Alamos National Laboratory reached what federal officials say is a key milestone in developing its first plutonium pit that can be placed in a nuclear warhead as it seeks to produce 30 of the bomb cores yearly by the end of the decade.

A prototypical pit — a hollow sphere about the size of a bowling ball — fared well in various tests conducted by California’s Lawrence Livermore National Laboratory, establishing it as a solid model with reliable data the Los Alamos lab can use to meet its goal of developing the first usable “war reserve” pit this year.

Lab and nuclear security managers weren’t available Monday to comment because of the federal holiday. But in a recent interview with The New Mexican, lab Director Thom Mason said he was confident his teams would roll out the first war reserve pit this year that can be used in a nuclear weapon.

“This year is when we’re working to make the first certified, diamond-stamped, ‘Good Housekeeping Seal of approval’ pit,” Mason said. “We’ll make more after that.”

Lawrence Livermore’s testing determined the model pit is the most “high fidelity” plutonium bomb core the lab has fashioned in the current program, putting it on track to achieve its early pit production goals, according to the lab’s monthly newsletter.

These would not be the first war reserve pits the lab has manufactured. For a short time more than a decade ago, the lab produced 10 pits a year for Navy missiles before its plutonium facility was shut down for three years because of safety violations.

Federal officials have indicated the process had to be revamped and new equipment installed to make pits for two warheads being developed.

The new W87-1 warhead will be key in replacing the outdated Minuteman class of missile with a next-generation intercontinental ballistic missile called the Sentinel. The pits also will equip the new W93 warhead, designed by the lab to be launched from submarines.

Even with the new devices, Pentagon leaders have said they don’t aim to make the nation’s arsenal larger but will replace aging or outdated systems with newer ones to deter nuclear adversaries.

Still, with Russia, China and North Korea growing more aggressive, some White House officials have expressed willingness to expand the stockpile.

If all goes as planned, the lab will produce the first war reserve pit in the current program roughly a year later than the original target.

A timeline mandated several years ago in the National Defense Authorization Act called for the lab to produce the first pit in 2023, 10 pits in 2024, 20 pits the year after that and 30 pits by the end of 2026.

But with a nearly yearlong production delay during the pandemic and vital equipment expected to arrive years later than hoped, the Government Accountability Office estimated in a 2023 report that 2030 was a more realistic target for the lab to produce 30 pits.

It could take the lab an additional two years to obtain the backup equipment needed, in case of mechanical breakdowns, to reliably make that volume of pits, the GAO said.

Mason thinks the lab can reach the 30-pit goal a bit sooner.

“We’re shooting for 2028,” Mason said. “There is a mission driver. We need to start making pits for this Sentinel ICBM.”

In the past year, the lab made 14 “development” or prototypical pits, he said, showing it has the basic production capability to move toward 30 pits.

An anti-nuclear activist said the lab might be approaching the point of making its first war reserve pit, but he believes it has a long way to go to manufacture 30.

In response to the lab director’s timeline, Greg Mello, executive director of the Los Alamos Study Group, said it’s advantageous to the lab for Mason to be optimistic, while nuclear security managers, military leaders and congressional watchdogs like the GAO must be more realistic.

Touting the first war reserve pit about to roll off the line is a way to give a positive outlook as Congress prepares to take up the budget, Mello said.

“They’ve had a lot of bad news in term of schedule [delays],” he added. “They’re trying to make it look like they’re back on schedule.”


Greg Mello published comment:

Thanks for the good article, Scott. I would add that on January 31st, NNSA Administrator Jill Hruby said, at a conference in Washington, that the NNSA aims to have the Savannah River Site's (SRS's) new pit factory -- a partially-built, never-used, plutonium/uranium nuclear reactor fuel factory now in the early stages of re-construction -- making W93 pits by 2035. Construction at SRS is supposed to be complete by 2032, the same year that NNSA now says re-tooling for pit production will be complete in the Los Alamos plutonium facility.

What was new in Ms. Hruby's speech was that SRS is to produce W93 pits (for Trident submarine-launched missiles), rather than W87-1 pits (for new silo-based missiles). So LANL's production, if it proceeds as planned, is to be entirely for the W87-1/Sentinel fleet until the required (classified) number of W87-1 pits have been produced, whenever that is. Meanwhile, the roughly $140 billion Sentinel project has experienced a large cost overrun, triggering Pentagon review. I believe even more expensive problems with silo reconstruction will be found when construction begins.

Many senior military leaders, not just independent analysts, academics, and peace activists, have questioned the value of silo-based missiles altogether. We believe the ICBM force should be scrapped -- followed by the rest of the U.S. arsenal, a goal to which the United States and all other major nuclear states are committed by law.

Reliable production at LANL will be, according to NNSA and GAO, 6 years later than promised. NNSA will have spent by then some $21 billion setting up LANL production, of which $7 billion has already been spent. In crude terms, this is about 6 times NNSA's 2017 cost estimate. Production will have to be 24/7, because LANL's facility is so small and crowded -- about 1,000 people are working there compared to the "100" NNSA told Congress were originally projected for the facility. Again according to the same NNSA report to Congress, the LANL facility is not projected to last beyond 2045. (Risks for Sustainment of PF-4 at LANL, Report to Congress, Nov 2020, obtained by FOIA, redacted.)

As readers of these comments know, we see no national security value in turning LANL into a production plant under any but the most hawkish nuclear policies. What is actually necessary for the United States to prosper is to turn away from the new nuclear arms race toward international cooperation. We can't begin to "win" an arms race, no matter how "winning" is defined. Russia and China both have greater industrial capacity for war and nuclear weapons production than does the U.S. Baiting the bear and the dragon may be a recipe for a few corporate profits and individual fortunes, but it will bankrupt the rest of the country and drive many of our people into poverty and spiritual despair. We are already quite close to that.

Current "defense" and nuclear weapons expenditures are running at about $7,600 per household per year, and debt service on the $34 trillion or so in federal debt now outstanding is about that much again. This is a crushing load. In addition, sucking skilled workers into military production takes them away from the productive contributions they could be making in our society, which badly needs engineers, craft workers, and administrators to rebuild our crumbling future. It is our cities and our countryside that need rebuilding, not our nuclear arsenal. Let that arsenal decrease and seek cooperation, not confrontation and mutual terror ("de-terr-ence"). It will take time, now that we have wrecked our foreign relations so badly. The best time to stop ravaging and start replanting the orchard of peace and cooperation is always now, so our children can be fed from its fruit. We need realism and we also need faith -- as in the name of this newspaper and this city.

^ back to top

2901 Summit Place NE Albuquerque, NM 87106, Phone: 505-265-1200