Brief Notes to the Administrative and Legal Processes
Underway which Affect the Continuing Disposal of Nuclear Waste at Los
Alamos and the Prospects for Cleaning Up Contaminated Sites there.
Greg Mello
July 18, 2002
These matters are
difficult to fully understand. The following represents only a partial understanding and
we welcome discussion on it. Feel
free to call or write.
1. The New Mexico
Environment Department (NMED) Issued a Finding of Imminent and Substantial
Endangerment (Finding) on May
2, 2002 for Los Alamos National Laboratory
(LANL).
This Finding is in itself a good thing and it is very strong both factually
and legally. It is based, however, on a section of the New Mexico
Hazardous Waste Act, NMSA §§ 74-4-10.1, which has no provision for public
participation, no specific right of public appeal, and provides no authority
to order actual cleanup. It was not at all necessary to base an
order to clean up the site on this particular law, which has these serious
limitations. In effect, NMED's exclusive
choice of this legal basis is equivalent to saying that the $701 million
spent so far investigating the site over a 12-year period provides too
little basis for any actual cleanup decisions.
NMED's Finding does
not say that there actually is any imminent and substantial endangerment
to human health and the environment, but that there may be such endangerment,
which is the legal standard in this particular part of the
statute. It is this distinction, between what is and what might
be, which leads to authority in this law for investigation but not for
an actual cleanup order.
Historically, this limitation in federal hazardous
waste law (the Resource Conservation and Recovery Act, or RCRA) was widely
recognized in the early 1980s and led to passage of the federal Hazardous
and Solid Waste Amendments of 1984 (HSWA). We can thus liken the
choice of this particular legal basis for the Corrective Action Order
(CAO; #2, below) to "turning back the RCRA clock" to before HSWA and,
at this site, to before all the expensive work that has been done pursuant
to HSWA at Los Alamos. The CAO asks for LANL
to summarize this prior work, but does not use the facts already known
to order any actual reduction of risk, i.e. cleanup. It is as if
NMED can't, or won't, use the roomful of reports it has already been given.
2. NMED issued a
Corrective Action Order (CAO) consequent to the Finding, also on May 2, 2002.
The CAO is an order to do a great deal of investigative work at LANL over
a period of several years. To oversimplify, the great bulk of the
work is oriented toward risk assessment and is largely irrelevant to remedy
selection.
DOE has estimated that the work ordered in the
CAO would cost about $65 M the first year, and presumably a comparable
amount in subsequent years. DOE also estimates that LANL will get
a total of $76 M next year as a result of the Letter of Intent (LOI; #3
below), or just a little more than DOE originally estimated would be necessary
to do the work required by the order. The work to be done under
the CAO will therefore supersede essentially all other cleanup activity
at the site, making any but a very small amount of actual cleanup fiscally
impossible for the foreseeable future.
It is likely that the work required in the CAO
will continue throughout much if not all of the coming gubernatorial administration
- and therefore tie the hands of that administration. On the national
level, performance of the work ordered in the CAO will probably occupy
all of the current administration and some of the next, leaving time for
superficial capping and final "completion" by 2008, as the DOE timetables
and budgets developed to support the LOI show.
It should be emphasized that the CAO and the
LOI are two sides of one coin. The LOI provides money to the site
(and the NMED) to do the work described in the CAO. The CAO in turn
is palatable to DOE and UC because it supports the vision described in
the LOI, and will become more supportive through DOE/UC/NMED negotiation.
The final result of this negotiation may be "fixed" by being recorded
in a court as a settlement (#s 4 and 5, below).
It must also be emphasized that there is no requirement
for NMED to consider any public comment whatsoever as it finalizes the
CAO. There is also no explicit and specific public right of appeal
for the final CAO.
The defects of the CAO have been described in
greater detail in the Study Group 5/8/02
press release.
3. The Letter of
Intent (LOI) was signed by all parties on or about May 30, 2002.
The LOI has been described in greater detail elsewhere (i.e. in b and
c above). It is the master document loosely governing all the processes
listed here. Formally, it means little. Practically, it -
and the several tens of millions of dollars that go with it - mean a great
deal. It is, quite possibly, determinative.
In the LOI, NMED agrees to DOE's
overall cleanup plan - to expediting TRU disposal, to DOE's
approach to risk analysis, to a secret decision-making process, and other
substantive matters. As a result, NMED gets paid by DOE an unstated
but large amount more than it already receives from DOE, under a new protocol
defined by the LOI and any related or supporting documents, which may
or may not be public. This new payment will be, according to DOE, approximately $700,000 for FY03.
DOE is taking this and other LOIs
to Congress and using them as evidence of state "buy-in" to gain final
congressional approval for the idea of an "accelerated cleanup fund,"
probably with guidelines that Congress may impose, and to secure funding
for it. DOE can then use this fund next year and in subsequent years
to exert leverage on the states - to "buy down" cleanup standards, humble
the regulators, and streamline decisionmaking
processes in ways that sandbag any opposition.
4. On June 2, 2002, the University of California (UC) filed a lawsuit in U.S.
court (not yet served on defendant NMED as of this writing) seeking declaratory
and injunctive relief against the Finding and the associated Corrective
Action Order.
This lawsuit is clearly being used as a negotiating tool - a hammer -
and may be dropped or settled if NMED does what UC wants NMED to do. It could also help NMED save face after these negotiations when the day
is done.
The most important part of this lawsuit may be
the claim that the Finding and CAO (which UC claims are inseparable) violate
both procedural and substantive due process obligations under RCRA, since
they appear to be modifications of the LANL RCRA operating permit, specifically
the HSWA (corrective action) portion of it. (The other claims made
by DOE do not seem as important or meritorious at this time, at least
at first glance, although their sweeping nature create high stakes for
NMED and the public, should a struggle along those lines be joined. This, and especially the work involved, is why they are an effective threat.)
This due process argument appears to have considerable
merit, to say the least. In a meeting with the Study Group on 7/5/02, NMED officials Maggiore, Ritzma, Lewis, and Will
admitted that HSWA corrective action, and also RCRA closure and post-closure
care under the permit, were indeed the content and purpose of the CAO.
They even said that the CAO might be - subsequent to being finalized,
we must presume, without public hearings - incorporated into the permit.
The hearing process used for the permit would then "bless" and legitimize
the CAO without actually providing a substantive hearing of the issues
involved. (NMED has agreed, in the LOI, to avoid such uncertain
processes.)
This lawsuit could also be a means to solidify
or "fix" the outcome of decisions and place them beyond the reach of the
public by recording them as an official settlement of the case.
Or, if the public process were going "badly," the lawsuit could be served
and another, higher, negotiating forum opened up - one with a high cost
of admission that can keep out the rabble.
Interestingly, DOE is not party to this lawsuit,
although DOE will pay for it on a cost-plus basis (i.e. at no charge to
UC). Some of the arguments appear too explosive or ill-founded to
be made by DOE or DOJ, in all likelihood. For staging a harassing
action like this one, UC has more freedom than DOE.
5. On June 2, 2002, DOE and DOJ have appealed
the Finding and associated CAO in state court.
This lawsuit is also inactive at this time. It helps preserve DOE's interests against NMED vis-a-vis
the CAO - which is to say, the entire cleanup agenda at LANL for the foreseeable
future) - and also against UC's federal lawsuit,
i.e. UC itself.
6. A heretofore-secret
process for closure and post-closure plan submittal and review, covering
areas G, H, and L at TA-54, is now underway at NMED.
On April 25, 2002,
DOE and UC submitted proposed closure plans for the three TA-54 hazardous
waste disposal sites G, H, and L, pursuant to a process formally begun
in secret by NMED in December of 2001. After letters from the New
Mexico Attorney General, more than 2,000 individuals, and 27 environmental
organizations requesting closure of Area G, it is very strange that none
of these people and organizations were notified that this process had
begun, and that very substantive decisions were being made in it.
The plan submitted for Area H is based on HSWA
corrective action requirements (which are very vague) rather than more
specific RCRA closure requirements, which was done in response to a (also
secret) NMED go-ahead given on ??[2001]. This
was a substantive and very significant permit decision. There was
no public knowledge or input, let alone a hearing.
This Area H "clean-up" is expected (by both NMED
and DOE) to set a precedent for remedies at all other disposal sites at
LANL, and is for this reason DOE has made it the subject of a "high-performing
team" (see #7, below), as well as a (separate, public-relations-contractor-
led) "focused stakeholder involvement" process. In other words,
the RCRA public participation requirements are being violated at what
both NMED and DOE managers consider the bellwether site.
Months ago, both NMED and DOE officials told
the Study Group orally that no decisions were being made in the meetings
organized by the PR contractor regarding Area H. This appears to
be belied by the correspondence record between these parties. NMED
never replied to our letter of protest about this process.
NMED senior management told us on 7/5/02
that the closure plans for these sites - G, L, and possibly they meant
H as well - could not be approved in their current form. They also
said, however, that they have not advised LANL in detail as to what approvable
plans should contain. A second notice of deficiency has been sent
(May 2, 2002); a revised set of plans
is reportedly due from LANL on August 15.
In theory, this would set the stage for a "train
wreck" this fall, when the draft permit is to be released for comment,
because any approved permit must have an approved closure plan, and the
preparation of a final, solid closure plan from the present level of effort
(as evidenced by the April LANL drafts) would probably take not less than
a full year, if not much more. (Los Alamos has been required to
have binding closure plans on file since - sit down now - 1980.)
The way NMED proposes to side-step this train
wreck - and sandbag all the public interest expressed in the Study Group
"Can-Paign" and elsewhere - is by issuing a closure plan that sets
up what senior NMED officials call a "process" for writing a closure plan.
The first step, the one to be taken this fall, is to approve a framework
for studying background issues at the site, a step prior (if related at
all) to the investigations needed to propose alternative remedies for
the site. And that framework will be, as they said to us, the CAO!
Thus the CAO will substitute for not just for the HSWA part of the LANL
permit, but for the closure and post-closure plans as well. It will
be, as NMED said to us on 7/5/02,
"the first step in closure." Thus, NMED will approve "a plan for
a plan."
Since the work required by the CAO will take
years, it won't be concluded when Area G reaches full capacity and ceases
operation, probably within about 4 years. In this way, the question
of whether Area G needs to actually close will be delayed until it is
moot. One can't implement a closure plan that is only a research program,
aka the CAO. Nuclear waste disposal will,
by that time, be in full progress at another site - one without any known
exposure to RCRA regulation. And the next gubernatorial administration
will be over.
In effect, the CAO will take the closure of Area
G out of the hands of the next governor for his entire term.
In its April closure plans, DOE asserts, in defiance
of NMED so far, that only one shaft and one pit at Area G have received
regulated hazardous waste and need close, and
therefore that "Area G" is not the site operationally known as Area G. Really.
7. "High-Performance
Teams" (HPTs) are now meeting and making various
preliminary (but likely to be permanent) decisions.
There are three or four, or possibly more, HPTs,
composed of the regulators and regulated, meeting privately to vet the
range of possible corrective actions and closure remedies for various
sites. "Any decision made [in one of these groups] would then be
brought into the public notice and comment process," said Greg Lewis on
7/5/02. This is the private process to which NMED is
committed by means of the LOI (#3, above). These HPTs
reportedly include teams for the "Airport Landfill," for "TA-16," and
for "Material Disposal Areas" generally, of which "Area H" is a subset. It is to prevent this kind of decision-making that open-government laws
have been enacted in our society.
8. A draft RCRA operating
permit for LANL (Permit) will be issued by NMED circa October 1, 2002
It will include a corrective action (HSWA) module. It may include
the CAO by reference, quite possibly the product of a negotiated (private)
settlement between UC and NMED, because of the lawsuits filed in 4. and/or
5. above. The annual installation
work plan (IWP) is already in place (no public hearings were held on the
IWP in this or any year); the work plan of the CAO will almost certainly
replace this portion of the permit.
There will be public notice and hearings during
this process, as the law requires, but the main decisions on cleanup and
closure will have already been made under items 2, 3, 4, 5, 6, 7, and
possibly 11, and what is not already fixed may be approved as a "process,"
something which can be defined as time and research go on, provided DOE
fully funds the project. Those who fund the work will largely determine
the nature of the work, both at LANL and at NMED, which is becoming more
and more of a "consulting firm" to LANL as a result of these processes.
Actions constrained by items 4 and 5 may be firmly
fixed, i.e. fixed beyond the legal reach of third parties who are not
parties to the litigation and appeal. In this way the product of
UC/DOE/NMED negotiations, which includes part of the outcome of the HPT
process (item 7) could become "frozen" beyond the reach of the public.
Meanwhile the range of remedies for HSWA corrective
action and closure/post-closure would, according to DOE, be gravely constrained
by item 9, should it pass and become law.
9. The Environmental
Covenant Act (ECA)
The ECA was originally proposed for passage last year, but was withdrawn
and recast instead as a memorial which simply endorsed the ideas of the
law and called for NMED to draft it. It was defeated (largely by
the Los Alamos Study Group and allies), but the act is quite likely to
be resubmitted to the legislature again this coming year.
The ECA is a means to at least two ends. First, the ECA will establish a new exit clause for corrective action
requirements under most, if not all, New Mexico environmental laws, namely "technical infeasibility." For such sites,
it will enshrine alternative land use, or restrictive zoning - i.e. regulation
of the public, rather than the polluters - as a remedy option for essentially
any site. Thus DOE would have statutory relief from residential
and agricultural cleanup standards.
Second, for many contaminated sites, it will
grant an pollution "easement" to the NMED, in effect making the NMED
the owner of a real property interest in - pollution! NMED would
be responsible for maintaining any environmental treatment works on the
property and for enforcing land use (zoning) restrictions. This
would be helpful in removing liability for any contamination on the large
amounts of excess property DOE wishes to give away to local government
and tribes, some of which is contaminated.
10. Performance Assessment
(PA) process for Area G
This is a non-RCRA process, but the work done in it will underlie the
RCRA choices made at this site. Under DOE Order 435.1 [ck], DOE
must undertake an internal "licensing" process for its nuclear waste disposal
sites, in some ways comparable to the formal licensing provided by the
Nuclear Regulatory Commission (NRC) for commercial low-level waste (LLW)
sites. (A question arises as to whether there is a legal standard
DOE must meet (e.g. "substantially the same" as the NRC process, perhaps
in the Atomic Energy Act or another statute.) A team composed of
DOE managers reviews a technical risk assessment for the site, called
a Performance Assessment (PA). The current PA is known to be badly
deficient. A new PA is to be released in early 2004, near the date
when Area G is supposed to close (!). Substantively, the new PA
will be largely applicable to the new disposal site, which is likely to
be directly adjacent to Area G. Area G, for all its problems, is
likely to be a better, possibly a significantly better, nuclear waste
disposal site than any other site at LANL. It was well-chosen among
the possible sites at LANL.
11. The "annual unit
audit" process
NMED assesses hazardous waste fees based on the number of regulated "units"
at a facility. Up to last year at least, LANL always asserted that
Area G is one unit. Now LANL seeks to close a small portion of Area
G, and leave the rest open as another unit, or several other units, for
all we know. LANL asserts in its closure plan that it is in negotiations
related to the annual unit audit process that the identity of Area G -
the portion requiring closure - will be decided, rather than in an open
permitting process. NMED officials tell us this is not the case.
NMED will probably receive more fees if Area
G is split into many units, potentially giving NMED a serious negative
incentive to "wholistic" closure of the site.
12. NMED enforcement
actions at LANL
These exist but I do not have details about them. Each will create
a separate negotiating forum at which a localized solution is found to
the disputed regulatory finding in question, forums in which the public
has not been involved. In theory, we could be. If not protested
in a timely manner, these settlements will stand, and will bind NMED's
future choices, and will not be revisited in future permit hearings.
13. Permit modifications
A number of permit modifications have been written and approved for LANL,
none of which has gone to public hearing with the possible exception of
the incinerator in the mid-1990s. It will be difficult to "undo" any of these past decisions.
It should be repeated that, upon information
and belief, and other than the incinerator hearing and the initial hearings
conducted by EPA in 1989 (and then only on the HSWA module of the permit?)
no public hearing has ever been convened for the LANL permit.
Upon information and belief, the LANL RCRA permit
was issued, modified many times, ran its course, expired, and is now "continued"
in some fashion pending NMED approval of a new permit, all without a single
hearing ever having been held by NMED. Amazingly, even the expired
permit has been modified several times, of course without a public hearing.
It is in the formal permit modification process
that NMED could enforce cleanup requirements on LANL. Permits, including
their modifications, are explicitly open to citizen lawsuits to compel
compliance.
|