![]() |
|
For immediate release: June 8, 2026
Plutonium "pit" production now a $60 billion program -- $20 billion down, $40 billion to go Contact: Greg Mello: 505-577-8563 Albuquerque, NM -- Today the Los Alamos Study Group released updated cost estimates for the acquisition of plutonium warhead core ("pit") production capability at Los Alamos National Laboratory (LANL) in New Mexico, the Savannah River Site (SRS) in South Carolina, and other sites.
The estimate is based on the President's budget request (PBR) (here and here) for the National Nuclear Security Administration (NNSA) for fiscal year 2027 (FY27) and prior PBRs.
In its estimates, the Study Group relied on enacted prior-year spending, NNSA's request for FY27, NNSA's estimated future spending through FY31, and near-term extrapolations from these.
Program (operational) spending was included through the years in which NNSA estimates pit production construction would be complete at each site (FY34 at LANL, FY35 at the earliest for SRS).
NNSA has not yet produced "baseline" pit construction cost estimates for the main pit projects at either site, but claims it will produce ones for both sites by September 30, 2026. (This milestone is called "Critical Decision 2/3" in the data sheets for these projects.)
At SRS, essentially all pit-related construction falls within the scope of the Savannah River Plutonium Processing Facility (SRPPF) project, which has been assigned a $25 billion (B) "placeholder" cost, pending approval of a project baseline.
At LANL, acquiring pit production capability requires many different construction, remodeling, and equipment installation projects as well as a large annual program budget. The program budget is used not just for operational purposes but also for many smaller capital projects (costing up to tens of millions of dollars) as well as equipment.
One big LANL project, the Chemistry and Metallurgy Research Replacement (CMRR) project, has become a "basket" for various evolving subprojects across multiple buildings, with a projected overall timeline that is now expected to stretch from 2004 to 2034.
Even after NNSA produces baselines for its big pit projects, large cost uncertainties of several kinds will remain. What we have done is to make the best estimates we can with the data available, while also reporting the assumptions we used.
In addition to the two main sites, pit production also involves work, and costs, at Lawrence Livermore National Laboratory (LLNL), the Nevada National Security Site (NNSS), the Kansas City National Security Campus (KCNSC), and possibly Pantex. Recent speeches by NNSA officials (in Study Group files) and other available documents suggest LLNL, NNSS, and SRS may all three be newly-tasked with assisting LANL's pit mission.
Takeaways, under the assumptions we report, include these:
For reference, total Manhattan Project costs through December 31, 1945 were $46.5 billion, if updated to April 2026 dollars using the Bureau of Labor Statistics inflation calculator (see Schwartz et. al., Atomic Audit, p. 60).
For further background please see Current & historical cost estimates for reconstituting plutonium pit production, details, Aug 29, 2025 and its references. Further background on pit production more generally can be found here (LANL and general references) and here (for SRS).
Study Group director Greg Mello:
***ENDS*** |
|||
|
|
|||
|